Holding this certification demonstrates that an individual has the technical skills and knowledge required to perform SAP S/4HANA system conversions and upgrades. This certification is highly valued in the market and is recognized by employers as a testament to an individual's expertise in this field. It opens up new career opportunities and can lead to higher compensation and job satisfaction.
The certification is ideal for SAP consultants, project managers, and IT professionals who are responsible for managing SAP system upgrades and conversions. It is also a valuable asset for organizations looking to enhance their IT capabilities and streamline their business processes.
NEW QUESTION # 40
You want to perform an SAP S/4HANA conversion using SUM with DMO. Which steps run before the beginning of the technical downtime, independent of your SUM configuration?
There are 3 correct answers to this question.
Response:
- A. Import of upgrade and language data from the download directory in phase TABIM UPG
- B. Generation of the new ABAP loads in phase RUN_SGEN_GENER8
- C. Creation of application tables in the SAP HANA database in phase EU_CLONE_MIG_DT_CREATE
- D. Import of dictionary objects from the download directory in phase DDIC_UPG
- E. Activation of dictionary objects in phase ACT_UPG
Answer: A,D,E
NEW QUESTION # 41
What can you achieve by setting the SUM parameter "migration_only" to 1 in parameter file SAPup_add.par?
Please choose the correct answer.
Response:
- A. An SAP S/4HANA conversion is performed, without adapting the customer data.
- B. A migration of the SAP system to a new hardware is performed, without performing an SAP S/4HANA conversion.
- C. A change of the database type is performed, without changing the software components.
- D. An upgrade of the software components is performed, without changing the database type.
Answer: C
NEW QUESTION # 42
In which case can you use near-Zero Downtime Maintenance (nZDM)? Note: There are 2 correct answers to this question.
- A. When upgrading an SAP ECC system with DMO
- B. When upgrading an SAP S/4HANA Server system
- C. When performing an SAP S/4HANA conversion without u DMO
- D. When performing an SAP S/4HANA conversion with DMO
Answer: A,B
NEW QUESTION # 43
You are using the maintenance planner to calculate the required software components for your SAP S4HANA conversion. What do you need to know regarding SUM?
- A. AA
- B. As soon as the next SP level of SUM is available, the current version of SUM passes into "patch on request mode" immediately.
Answer: B
NEW QUESTION # 44
What phases of SUM will be executed during an SAP S/4HANA conversion including DMO?
There are 3 correct answers to this question.
Response:
- A. Phases DIFF*
- B. Phases EU_IMPORT*
- C. Phase DOWNCONF_DTTRANS
- D. Phase RUN_RSPTBFIL _ISUTABU
- E. Phase RUN_RSDBSCPY
Answer: A,B,C
NEW QUESTION # 45
Which of the following are valid options to check the progress of an inplace SUM DMO run? Note There are 2 correct answers to this question
- A. Check the dump size of the database export on disk.
- B. Check logs for jobs starting with RSUPG_SGEN in the SAP system.
- C. Check the Charts Control Center in the SUM Ul
- D. Check the log files written in the SUM directory subdirectory abap. subdirectory log
Answer: A,D
NEW QUESTION # 46
Unicode migration ECC on MaxDB to HANA in scale out what should we consider.
- A. DMO can only be run with systems NW740 or NW731
- B. Target DB size will increase temporarily
- C. A
Answer: A,B
NEW QUESTION # 47
SUM was registered at the SAP Host Agent. Based on which information does the SAP Host Agent determine the path to the SUM directory.
- A. The path was stored in file host_profile during registration
- B. The path was stored in file sumabap conf during registration
- C. The path was stored to the environment of user <sid>adm during registration
- D. The path is taken from the URL entered in the browser to start SUM
Answer: B
NEW QUESTION # 48
You are planning an SAP S/4HANA conversion. Which conversion-specific tasks need to be performed during the preparation phase?
There are 2 correct answers to this question.
Response:
- A. Perform the migration of data into the new data structure
- B. Run the database migration to the SAP HANA database
- C. Apply the recommendations of the simplification list
- D. Check the compatibility of custom code with SAP S/4HANA
Answer: C,D
NEW QUESTION # 49
What do you need to consider when performing the SI checks for an SAP S'4I 1ANA conversion? Note There are 2 correct answers to this question.
- A. You need an SAP system based on AS ABAP 7.50 or above for the SI check framework
- B. You need to build up an SI check framework by applying SAP Notes
- C. The SI checks are executed in the development system and the results are transported into the subsequent systems
- D. The errors from the SI checks must be solved, otherwise. SUM will report an error
Answer: A,B
NEW QUESTION # 50
You are using DMO of SUM. You defined 40 parallel R3load processes during uptime and 80 parallel R3load processes during downtime.
The server provides 8 CPU cores. Phase EU_CLONE_MIG_DT_RUN is running. In the Charts Control Center you can see 40 Process Buckets being executed in parallel.
Why are 40 Process Buckets executed in parallel?
Please choose the correct answer.
Response:
- A. There is a maximum of 40 parallel R31oad processes within this specific downtime phase.
- B. SUM is still running in uptime; the number of 40 defined R31oad processes is considered.
- C. The number of CPU cores does not allow more than 40 R31oad processes to be run in parallel.
- D. These are 40 pairs of R3load processes, so there are 80 R3load processes running.
Answer: D
NEW QUESTION # 51
What is the main purpose of performing benchmark runs for an SAP S/4HANA conversion?
- A. To optimize the activation
- B. To optimize the main import
- C. To optimize the conversion
- D. To optimize the migration
Answer: D
NEW QUESTION # 52
You are preparing for a standard SAP S/4HANA conversion from SAP ECC on Windows with SAP MaxDB to SAP S/4HAN. You are performing the corresponding maintenance transaction with the Maintenance Planner. Which kernels do you need to select for the SAP S/4HANA conversion?
There are 2 correct answers to this question.
- A. Kernel for target release, Windows, SAP HANA
- B. Kernel for target release, Windows, SAP MaxDB
- C. Kernel for target release, Linux, SAP HANA
- D. Kernel for source release, Windows, SAP MaxDB
Answer: A,D
NEW QUESTION # 53
What is the different between the benchmaking and the repetition option of the Database Migration Option (DMO) of SUM?
- A. The benchmaking option allows you to migration a specified set of tables
- B. The repetition option allows you to repeat the complete migration
- C. The benchmaking option allows you to repeat the uptime migration
- D. The repetition option allows you to run the migration without a shadow system
Answer: A
NEW QUESTION # 54
You are performing an SAP S/4HANA conversion. You are in the BIND_PATCH phase of the Configuration roadmap step. For some software components, you find entries in the Calculated level column. What does the Calculated level indicate for those software components?
- A. The SAP support packages contained in the upgrade media, calculated by the maintenance planner
- B. The SAP support packages of the support package stack, calculated by the maintenance planner
- C. The SAP support packages that will be bound to the conversion
- D. The SAP support packages in the download directory that are newer than the selected support package stack
Answer: D
NEW QUESTION # 55
How does SUM recognize modification adjustment transports from predecessor systems?
Please choose the correct answer.
Response:
- A. By searching for transport requests that are assigned to the project SAP_ADJUST
- B. By searching for transport requests in the file umodauto.Ist
- C. By searching for transport requests named <SID>K0<number>
- D. By searching for transport requests in DIR_TRANS, subdirectory "transport"
Answer: B
NEW QUESTION # 56
You downloaded content from the SAP note 1000009 ("ASU Toolbox 2008"). Which transaction needs to be executed to use that content in the ASU Toolbox?
Please choose the correct answer.
Response:
- A. /ASU/START (Start ASU Toolbox)
- B. /ASU/SHOW_NOTE (Show SAP Note via Web-Browser)
- C. /ASU/SSM (ASU Simple Schedule Manager)
- D. /ASU/UPGRADE (Start ASU Toolbox in Upgrade Mode)
Answer: A
NEW QUESTION # 57
Which are valid options to check the progress of the database migration in a Microsoft Windows environment?
There is correct answers to this question.
Response:
- A. Check the dump size of the database export on disk
- B. Check logs for jobs starting with "RSUPG_SGEN" in the system
- C. Check the log files written under "SUM\abap\log"
- D. Check the "Charts Control Center" in the SUM UI
Answer: C,D
NEW QUESTION # 58
During the upgrade of your development system, you run into the adjustment of non-dictionary objects handled by transaction SPAU There you find programs that are shown in status "automatic adjustment (green traffic tight). What will happen with these programs when you continue with your upgrade without performing any other actions inside your SAP system?
- A. SUM continues with the next phase and your modifications are kept as In the start release
- B. SUM refuses to continue unless you have marked a transport request as modification adjustment transport
- C. Before continuing with the next phase SUM asks for a modification adjustment transport
- D. SUM continues with the next phase and your modifications are lost
Answer: A
NEW QUESTION # 59
What do you need to know about the SAP ERP Upgrade and Update Guide?
There are 2 correct answers to this question.
Response:
- A. It contains a section "free space requirements"
- B. It is target release specific
- C. It contains a troubleshooting section
- D. It is a database-specific document
Answer: A,B
NEW QUESTION # 60
You are performing an S/4HANA conversion of the development system. Which credentials do you use in which system to perform the adjustment of dictionary objects (SPDD)?
Please choose the correct answer.
Response:
- A. Credentials of a named user in client 000 of the shadow system
- B. Credentials of user DDIC in client 000 of the shadow system
- C. Credentials of a named user in the development client of the development system
- D. Credentials of user DDIC in the development client of the development system
Answer: A